project image : Rhodia Chemical Plant

/apps/pbg/current/pbg/media/images/projects/rhodia-chemical-plant.jpg

Rhodia Chemical Plant

We began the project with demolition of the concrete slab so we could excavate another seven feet below the existing grade. A new, four-foot thick concrete foundation/slab, with a four-foot retaining wall, was then formed.

Features included:

  • 10’ X 6’ X 5’ sump pit with stainless steel lining and anchor bolts
  • Fabrication of structural piers and a separate foundation for a 12’ X 45’ future building
  • Fabrication of structural piers for Phase II pipe rack
  • A six-story steel structure
  • Placement of six chemical tanks, ranging from 6,0000 to 35,000 pounds