AFG Industries


AFG Industries

This design/build structural rehab project in a plant originally built in 1919 required us to shore and repair many of the deteriorated beams, columns, and slabs.

We repaired concrete columns, concrete beams, and suspended slabs. The work began with temporary shoring, sandblasting, and chipping to remove the decaying concrete. We then installed steel cage rebar around prepped columns before surrounding the columns with a 6-inch band of concrete.

Steel beams were placed at mid-span between the existing concrete beams to strengthen the existing slab. Some beams had to be installed in two pieces, then spliced together, because of the massive amount of process piping running through beam locations.

Overhead and column patching had to be hand troweled from lifts and scaffolding due to limited accessibility at those heights.

Shelby Waste Water Treatment Plant


Shelby Wastewater Treatment Plant

This project included several additions to an existing plant, as well as construction of new buildings.

The scope of the work included:

  • New aeration basin
  • Two new final clarifiers
  • 700,000 square foot compost building
  • Processing facility
  • Operations building
  • Blower building
  • Maintenance facility
  • Trickling filter, 140-ft. in diameter
  • New chlorine contact chamber

A substantial amount of the work was self-performed, including new mechanical piping and equipment, and all concrete work.

The concrete work included walls from 12 inches to 2 feet thick, a half-acre slab storage area, and slabs with metal hardener.

Subcontractor Resources